NOTE: This article is now archived.
Tumbleweed Ave Pathway Project Update
November 14, 2019
November 14th, 2019
TUMBLEWEED AVENUE PATHWAY CONSTRUCTION NOTICE
In July 2019, Council for the Town of Pincher Creek gave approval for the construction of a pathway along Tumbleweed Avenue (west of Ranchland Mall) to provide better connection between the new Thistle Crescent sidewalk and the existing pathway south of Ranchland Mall.
Due to the early fall snowstorms, construction has been delayed and the project will not be completed in 2019, however, the contractor is working diligently to complete portions of the construction this fall with the finishing touches occurring in spring 2020.
Tree removal began this week and pathway excavation/gravel base is expected to be constructed over the weekend (November 15-16) and into next week (November 18-22). Paving and landscaping, including the planting of replacement trees, will occur in spring 2020.
If you have any questions or concerns, please
contact:
Alexa Levair, CET, B. Tech
Capital Projects/Asset Coordinator
403-627-3156
Or submit a Citizen Request by visiting